Changes

Jump to navigation Jump to search

Masonry house

4 bytes removed, 01:24, 4 January 2013
# With the trowel activated, right-click the wall plan, and select ''Continue building'' until the [[wall]], [[window]], or [[sturdy door]] is finished.
* You need to have at least one stone brick and 2kg (as one piece) of mortar in your inventory to start a wall or continue building it. A wall needs 20 actions to finish, each action consuming one stone brick and 2kg of mortar.
* The stone brick and mortar will be consumed at the end of the action now.
* A building plan with no walls will decay in a few days, make sure you start at least one wall.
* The wall starts at 1QL. Each action including creating the wall adds (Mortar QL + Brick QL)/21 to the wall. The completed wall therefore has a quality of up to 1QL + 20 * (Mortar QL + Brick QL)/21. Depending on your masonry skill and quality of the tools you may get less on each action.
30

edits

Navigation menu